Case Study: Survey for laying of gas pipelines for Astha Power Corporation Private Limited
Astha Power Corporation Private Limited, Hyderabad, had proposed to lay a cross country pipeline (Indresham - Pashamyalaram pipeline) for transportation and distribution of Compressed Natural Gas (CNG) to various consumer locations from the tap off point of Reliance (RGTIS – MLV 13), Indresham village, Patancheru. This required systematic cross country pipeline route surveys along with engineering and cadastral surveys.
Three alternative routes were identified through a desktop study & field verification. A report was submitted on overall survey, which was carried out from Indresham to Pashamyalaram, which covered detailed engineering route survey for 14.482 km of the pipeline route. The survey covered about 50 meters on either side of centre line of the survey corridor.
The terrain of this segment exhibited nearly plain land with little variation in physiographic setting. The entire length of this segment traversed through non - forest area. Maximum care was taken to ensure its passage through non-agricultural land.
Scope of Work: Survey for laying of gas pipeline - 14.482-line kms.
- Reconnaissance Survey Report
- Route Maps on 1:5000 Scale
- Pipeline Survey Report
- DGPS Survey Report
- Alignment Sheets in drawing format
- Cross section engineering drawings
- Detailed Engineering Survey Report
- Population Density Survey